Planning

Seven days to mobilise: how we plan a solar site start-up

Kamran Malik4 min read

Engineers reviewing plans on a tablet in front of a solar plant under construction

The first week on site is when schedules are won or lost. With dedicated crews and our own equipment, we can mobilise quickly, but only when the preparation has been done.

Before we arrive

  • Drawings, set-out data and method statements reviewed and agreed.
  • Access, laydown areas and material deliveries confirmed.
  • Crew lists, training and equipment documents submitted.
  • Weekly output targets aligned with the master programme.

The first days

We start with a site induction, confirm the survey control and run a short trial section. Lessons from that first block are fed straight back into the plan, so the full-scale work begins with proven methods.